Estimating
Markup vs Margin Calculator: The Pricing Mistake Costing Contractors
Markup and margin sound interchangeable. They are not and confusing them is the most common pricing mistake in contracting. Markup is profit divided by cost; margin is profit divided by price. Because the denominators differ, the same dollars produce different percentages.
The 30% that isn't
Put a 30% markup on a $10,000 job: price = $10,000 × 1.30 = $13,000, profit $3,000. That $3,000 is 30% of cost but only 23% of the $13,000 price. If your business plan assumed a 30% margin, you are 7 points short before overhead even enters the picture.
The two directions of the same job:
- Bid from markup: price = cost × (1 + markup)
- Bid from margin: price = cost ÷ (1 − margin)
- To hit a true 30% margin on $10,000 of cost: $10,000 ÷ 0.70 = $14,286
Net true profit
Gross profit minus overhead recovery is net true profit the number that actually stays in the business. A job can show a healthy gross margin and still lose money once office, insurance, and truck costs are allocated. Run the margin math first, then subtract your overhead rate, and price the bid from that net target.
Related guides
Estimating
What Is a Material Takeoff? Net, Waste & Order Quantities Explained
What is a material takeoff in construction? Net is what the building needs, waste is what the jobsite eats, and order quantity is what the supplier sells.
October 5, 2026 · 5 min read
Concrete
How Much Concrete Do I Need for a Slab? Yards, Bags & Waste
How many yards of concrete do you need for a slab? Length × width × thickness ÷ 27 gives cubic yards — then add waste and choose ready-mix or bags.
October 2, 2026 · 6 min read
Masonry
How Many Concrete Blocks Do I Need? CMU, Mortar & Grout Guide
How many concrete blocks per square foot? Block counts, mortar bags, core-fill grout, and bond-beam rebar — the four quantities every block wall estimate needs.
September 24, 2026 · 7 min read